Stage Two | Construction Updates

As you approach settlement in the second half of 2017, you will be hearing from EG and Colliers International about the pre-settlement inspections and your lawyers will no doubt be in touch regarding the required paperwork.

Current Construction:

While Stage Two is still a wall of scaffolding, behind the blue curtain the silo window openings have all been created, so you can now peep through and see where each apartment will be.

Stage Two IMAG6282

The internal scaffolding is due to be removed. The internal loop road is currently under construction.

The tower crane will be coming down around February – March 2017.

??️

Our next update in March 2017 will have more details around next steps for Stage Two purchasers